Finally I am also wiedermal to carry on our blog. Slowly but surely it is really the home stretch, not only on the site ... We have also transported over the weekend quite a few car loads to move material from Biel-Benken after Fehren. A basement room is pretty full.
also works on the construction site every day something (no, "something" is quite a Understatement, it is equipped with various artisan batches in parallel with the completion of construction). The following is a brief outline of what each day has been done with:
- Friday, 08.31. : granite worktops kitchen, parquet completion
- weekend : reins Charge 1, detailed planning grounds / masonry with a friend / landscape architect or garden designer Luzi
- Monday, 03.09. : Supply and installation of balcony (Looks great, but for the foundations has once again committed a mistake somewhere -> see image below), completion of the cooking assembly, meeting with Mr. Rölli masonry, waterproofing garage
- Tuesday, 09.04. : masonry, electrical installation, heating / ventilation installations
- Wednesday, 09.05. : garage door installation, ventilation, sanitary equipment start-installations, electricians
So it's really something going on up there! In two weeks, but must also be ready in all (at least inside, the environment can also take a bit longer). What will be my view, a large and expensive chunks is the construction cleaning - luckily we do not do this yourself! That would be a horror, a few craftsmen namely (unerfreulicherweise actually - but it hardens with time, from) true qualities as a "pig in . Universe "proven by the dirt at all possible and impossible places
The story with the false floor is also last up cooked again, I had to -. Let's say neutral - treading a little unconventional ways But we have assurances and deadlines. get for the action "sanding and oiling" of the parquet.